Gold Coast Road Improvements

Gold Coast Road Improvements

A meeting was held in Torio last Monday (07/26/2010) between district, local and regional government officials and representatives from the 15+ road construction companies bidding for the contract to improve the current road from Atalya to Flores. Checkout Google Earth or Maps for area locations and details.

The government will award the contract on or about the 4th week of August 2010 and construction should begin shortly thereafter by the successful contractor.

The work will possibly be performed in the following stages:

  •  Stage 1 from Atalya to Mariato
  • Stage 2 from Mariato to Flores

The general plan is to widen the current road surface by 1 foot on each side as may be necessary and completely resurface it with new thick asphalt. It is expected to take between 18 and 24 months from start to finish.

It just keeps getting better and better – so come on down and visit us here on the Gold Coast of Panama – the Western Azuero peninsula.

Hope to see you soon!

 Tuck

This entry was posted in General, Travel. Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Connecting to %s